Seepage Control Measures for the Foundation of Xinglong Hydropower Project

ZHU Guo-sheng, ZHANG Jia-fa, LIU Xiao-jiang, LI Shao-long

Journal of Changjiang River Scientific Research Institute ›› 2016, Vol. 33 ›› Issue (5) : 145-150.

PDF(1798 KB)
PDF(1798 KB)
Journal of Changjiang River Scientific Research Institute ›› 2016, Vol. 33 ›› Issue (5) : 145-150. DOI: 10.11988/ckyyb.20151068
THE EIGHTH NATIONAL SYMPOSIUM OF HYDRAULIC SEEPAGE

Seepage Control Measures for the Foundation of Xinglong Hydropower Project

  • ZHU Guo-sheng1,2, ZHANG Jia-fa1,2, LIU Xiao-jiang3, LI Shao-long1,2
Author information +
History +

Abstract

Due to deep buried silty fine sand and sand gravel layers of strong permeability in the foundation of Xinglong hydropower project, the stability and seepage problem of the dam foundation are of great concern. By means of 3-D seepage analysis for the foundation of powerhouse segment and sluice segment, we compared the effects of different seepage control measures. Results reveal that under design water level condition, the exit gradient of foundation’s fine sand can be controlled less than 0.30 by taking some seepage control measures. When the downstream water level descents, the exit gradient of foundation fine sand will be larger than 0.30 behind the tail channel of powerhouse, and between 0.20 and 0.30 behind the sluice dam. The seepage stability of foundation fine sand is more relied on filter protection.

Key words

Xinglong hydropower project / seepage control / 3-D seepage analysis / coefficient of permeability / exit gradient

Cite this article

Download Citations
ZHU Guo-sheng, ZHANG Jia-fa, LIU Xiao-jiang, LI Shao-long. Seepage Control Measures for the Foundation of Xinglong Hydropower Project[J]. Journal of Changjiang River Scientific Research Institute. 2016, 33(5): 145-150 https://doi.org/10.11988/ckyyb.20151068

References

[1] 张家发. 土坝饱和与非饱和稳定渗流场的有限元分析[J]. 长江科学院院报,1994,11(3):41-45,57.
[2] 张家发. 三维饱和非饱和稳定非稳定渗流场的有限元模拟[J]. 长江科学院院报,1997,14(3):35-38.
[3] 任大春,吴昌瑜,朱国胜. 三峡二期围堰饱和-非饱和渗流分析[J]. 长江科学院院报,1997,14(2):44-47,56.
[4] 谢 红,张家发,龙文九. 三峡大坝基础渗流控制措施效果分析[J]. 长江科学院院报,1998,15(1):34-38.
[5] 谢 红,任大春. 三峡船闸高边坡渗流场三维有限元分析[J]. 人民长江,1996,27(3):6-9.
[6] 丁金华,任大春. 泄洪雾化降雨对水布垭大岩淌滑坡地下水分布的影响研究[J]. 长江科学院院报,2009,26(10):109-113.
[7] 张家发,杨启贵,熊泽斌,等. 水布垭面板堆石坝渗流场分析和分区材料允许比降设计指标研究[J]. 长江科学院院报,2008,25(6):71-76.
[8] 朱国胜,张家发,王金龙. 日冕水电站心墙堆石坝坝体渗流场初步分析[J]. 长江科学院院报, 2009,26(10):95-100.
[9] ZHU Guo-sheng, ZHANG Jia-fa, CUI Hao-dong,et al. Experiment Research on Fine Sand and Filter Material of Xing-long Hydroproject Dam Foundation[J]. Applied Mechanics and Materials,2014,(584-586):1956-1962.
[10]朱国胜. 汉江兴隆水利枢纽厂房及泄水闸坝段基础渗流控制措施研究[R]. 武汉:长江科学院,2010.
[11]SL265—2001,水闸设计规范[S]. 北京:中国水利水电出版社,2001.
[12]张俊霞,李 莉,朱登峰. 西霞院水库电站厂房坝段三维渗流计算分析[J]. 长江科学院院报,2009,26(10):67-70.
PDF(1798 KB)

Accesses

Citation

Detail

Sections
Recommended

/