JOURNAL OF YANGTZE RIVER SCIENTIFIC RESEARCH INSTI ›› 2014, Vol. 31 ›› Issue (5): 102-106,116.DOI: 10.3969/j.issn.1001-5485.2014.05.021

• CONSTRUCTION AND MANAGEMENT OF WATER CONSERVANCY PROJECTS • Previous Articles     Next Articles

Simulation of Flat-spread Concrete Placement in Roller Compacted Concrete Dam

DU Zhi-da, HAO Xue-ying   

  1. Faculty of Infrastructure Engineering, Dalian University of Technology, Dalian 116023, China
  • Received:2013-04-08 Revised:2014-05-12 Online:2014-05-12 Published:2014-05-12

Abstract: Most of the current simulation on concrete dam construction is based on the assumption that the construction period is mainly controlled by concrete mixing and transportation instead of by concrete placement surface construction. By establishing a model which simulates the flat placement surface construction, we analyzed the construction progress of roller compacted concrete dam with flat-spread technique in the presence of different placement surfaces. We demonstrated that the placement technique also has large influence on the construction progress. This model more truly reflects the concrete placement for roller compacted concrete dams.

Key words: roller compacted concrete dam, flat-spread placement, construction simulation

CLC Number: