长江科学院院报 ›› 2017, Vol. 34 ›› Issue (12): 111-114.DOI: 10.11988/ckyyb.20170408

• 水工结构与材料 • 上一篇    下一篇

自重施加方式对高拱坝廊道结构应力及配筋的影响

陈琴1, 2, 龚亚琦1, 2, 祁勇峰1, 2, 颉志强1, 2   

  1. 1.长江科学院 材料与结构研究所,武汉 430010;
    2.水利部水工程安全与病害防治工程技术研究中心,武汉 430010
  • 收稿日期:2017-04-14 出版日期:2017-12-01 发布日期:2017-12-22
  • 作者简介:陈琴(1971-),女,湖北钟祥人,高级工程师,硕士,主要从事水工结构数值分析工作,(电话)027-82829754(电子信箱)chenqin8317@163.com。
  • 基金资助:
    中央级公益性科研院所基本科研业务费项目(CKSF2016022/CL,CKSF2017040/CL)

Influence of the Way of Applying Gravity on Stress andReinforcement of Corridor in High Arch Dam

CHEN Qin1, 2, GONG Ya-qi1, 2, QI Yong-feng1, 2, XIE Zhi-qiang1, 2   

  1. 1.Material and Engineering Structure Department, Yangtze River Scientific Research Institute, Wuhan 430010, China;
    2.Research Center on Water Engineering Safety and Disaster Prevention of Ministry of Water Resources, Wuhan 430010, China
  • Received:2017-04-14 Published:2017-12-01 Online:2017-12-22

摘要: 自重工况一般是高拱坝内廊道配筋设计的控制工况,由于高拱坝施工过程的特殊性及复杂性,有限元计算中自重有多种施加方式。结合工程实例,对高拱坝基础廊道结构进行三维有限元分析,比较不同自重施加方式对廊道结构应力及配筋的影响。研究结果表明:按整体自重考虑时,廊道结构应力及配筋面积明显偏小;全部按分缝自重考虑时,廊道结构应力及配筋面积明显大于按施工过程考虑自重的结果;为符合实际施工过程及结构承载规律,保证结构安全及经济合理,在拱坝结构的有限元计算中应按照施工过程考虑自重荷载。该研究成果对泄洪孔结构的应力分析也具有参考价值。

关键词: 高拱坝, 廊道结构, 自重施加方式, 三维有限元, 配筋面积

Abstract: Gravity load case is generally the control condition of the reinforcement design of high arch dam. Because of the particularity and complexity of the construction process of high arch dam, there are several ways to apply gravity load, such as joint deadweight and whole deadweight. In this paper, the influence of gravity applying approach on corridor stress and reinforcement of high arch dam is studied through three-dimensional finite element analysis. Results show that in whole deadweight case, the stress and reinforcement area of the corridor structure are apparently small; while in joint deadweight case, the stress and reinforcement area of the corridor structure of are obviously larger than those of the deadweight results according to construction process. According to the actual construction process and the bearing capacity law of the structure, gravity load should be considered in the construction process in finite element calculation of arch dam to ensure structural safety and economic rationality. The research achievements could be taken as reference for the design of overflow outlet structure.

Key words: high arch dam, corridor structure, way of applying gravity, 3-D finite element, reinforcement area

中图分类号: