长江科学院院报 ›› 2006, Vol. 23 ›› Issue (6): 68-71.

• 岩土工程 • 上一篇    下一篇

水布垭面板坝智能土石方调配系统研究

  

  • 出版日期:2006-12-01 发布日期:2012-03-05

Research on Intelligent Earth-rock Volume Allocation System for Shuibuya Concrete Face Rockfill Dam

 JIANG  Cong-Feng, ZHAO  Ying-Hui   

  • Online:2006-12-01 Published:2012-03-05

摘要: 由于水布垭面板坝的土石方开挖量超过2 000万方,填筑量超过1 560万方,土石方调配问题关系到整个工程的进展和技术经济效益,为此分析 了水布垭面板坝土石方调配的特点,并根据数学模型,对水布垭面板坝智能土石方调配系统
进行了功能分析和系统设计。计算机仿真结果表明,该系统具有很好的实用性和可操作性, 响应时间约0.5~1 s,优于传统土石方调配结果。

Abstract: Total excavation volume of Shuibuya Project exceeds 20 million cubic meters and total filling volume of the dam is more than 15.60 million cubic meters. Its whole process and technic-economic benefit are considerably influenced by the earth-rock volumes allocation problem. Through analyzing the features of earth-rock volumes allocation of Shuibuya Project, an intelligent earth-rock volume allocation system was developed to model earth-rock allocation in construction. The results of computer simulation are technically feasible and better than those of traditional ways, and the response time of the database system is about 0.5-1.0 second.