Complex karst system was found in the impervious curtain line of Goupitan Hydropower Station. In view of the karst dam site, we designed and adopted a seepage surveillance system including osmometer, piezometer tubes, measuring weirs and other measures to comprehensively monitor the dam foundation. During the reservoir impoundment, the osmotic pressure of dam foundation has an obvious linear relationship with water level, but the maximum increase of osmotic pressure is only about 20% of that of reservoir water level. After the impoundment, the seepage pressure of dam foundation has no significant relevance with the reservoir water level. Monitoring results show that the overall effect of impervious curtain and karst blocking is obvious. The surveillance system provides a reliable scientific basis for evaluating the project safety.
TANG Ling
,
WANG Chao-qing
,
DUAN Guo-xue
. Seepage Monitoring for the Karst Dam Foundation of Goupitan Hydropower Station[J]. Journal of Changjiang River Scientific Research Institute, 2013
, 30(7)
: 38
-41
.
DOI: 10.3969/j.issn.1001-5485.2013.07.008
[1] 刘加龙,徐年丰,向能武,等.构皮滩电站防渗帷幕线上典型岩溶及处理技术[J].人民长江,2010,(22):44-46.(LIU Jia-long, XU Nian-feng, XIANG Neng-wu, et al. Typical Karst on Anti-seepage Curtain Line of Goupitan Hydropower Station and Its Treatment Technology[J].Yangtze River, 2010, (22):44-46.(in Chinese)
[2] DL/T 5178—2003,混凝土坝安全监测技术规范[S]. (DL/T 5178—2003,Technical Criteria of Concrete Dam Safety Monitoring[S].(in Chinese)
[3] 刘 鸣, 钟敬全,饶锡保, 等.牙塘水库大坝渗流监测分析及安全评价[J].长江科学院院报,2007,24(2):30-33.(LIU Ming, ZHONG Jing-quan, RAO Xi-bao, et al. Seepage Monitoring Analysis and Safety Assessment for Yatang Dam[J]. Journal of Yangtze River Scientific Research Institute, 2007,24(2) :30-33.(in Chinese)