JOURNAL OF YANGTZE RIVER SCIENTIFIC RESEARCH INSTI ›› 2014, Vol. 31 ›› Issue (1): 98-102.

• Orignal Article • Previous Articles     Next Articles

Integrated Innovations for Construction Management of China’s First Large Underground Water-sealed Oil Storage Cavern

LU Bao-qi1,LIANG Jian-yi1,ZHANG Wen-hui2,ZHAO Xiao2,CHEN Yan-sheng3   

  1. 1.National Petroleum Reserve Huangdao Base Co.Ltd.,Qingdao 266510,China;
    2.TGP Construction Headquarters of the Armed Police Hydropower Troops,Wuhan 430223,China;
    3.Key Laboratory of Geotechnical Mechanics and Engineering of MWR,Yangtze River Scientific Research Institute,Wuhan 430010,China
  • Received:2013-09-11 Revised:2014-01-06 Published:2014-01-01 Online:2014-01-06

Abstract: HD underground water-sealed cavern is China’s first large underground water-sealed oil storage cavern. In consideration of its construction characteristics,a construction mode involving integrated innovation,E(Engineering)+P(Procurement)+C(Construction)+Supervisor,and technical monitoring by a third-party is proposed. The framework of technology integration,knowledge integration,and organization integration is established,and the assessment system for integrated innovation is given. For the construction management of HD project,the proprietor,investigation,designing,construction,supervision and monitoring are integrated; the integrated innovation is further decomposed into three levels proprietor,supervision and construction; and the HSE control,quality control,schedule control,investment control,as well as contract control are implemented rigidly. Two years of practice at HD project shows that the implementation of integrated innovation has achieved excellent result.

Key words: oil reserve, integrated innovation for management, large cavern, groundwater sealed

CLC Number: