Analysis of Abrasion Causes at Inlet Bottom Sill of Desilting Outlet for Gezhouba Power Plant

LIU Dun-huang , JIANG Yao-zu , JIN Feng   

  1. Hydraulics Research Department, Yangtze River Scientific Research Institute, Wuhan 430010,China
  • Online:2010-06-01 Published:2012-07-27

Abstract:  Aiming at the problem of the abrasion at the bottom sill of emergency gate of desilting outlet of Gezhouba Power Plant, we recorded the flow state of the generator set inlet and the movement of sediment and gravels in the sediment-flushing inlet while the generator sets were running by the underwater photography. By observation, the character of the flow and the law of the sediment movement were gotten, the influencing factors of the abrasion at the bottom sill were analyzed, and some basic measures for avoiding abrasion were given.

Key words:  Gezhouba Power Plant , the sediment-flushing outlet , abrasion , cause analysis , measures for avoiding abrasion