The construction of traditional pile foundation is featured by environmental pollution, soil squeezing effect, low efficiency and high energy consumption. In an attempt to tackle these problems, the deformation characteristics and vibration of pile's surrounding soil during pile sinking and those of a high-rise bridge pier during adjacent subway running were investigated via in-situ pile sinking test and field vibration test. The resonance-free hydraulic vibratory hammer system was adopted for pile sinking test. Results demonstrated that the horizontal displacement of soil around the pile during pile sinking concentrated in the range of 0-2/3L(L represents pile length) near the ground surface, and in particular, the horizontal displacement in the range of 0-1/4L below the surface was very large. The maximum horizontal and vertical displacement of surrounding soil was 2.37 mm and 3.13 mm, respectively, and the inclination of the pier was 0.4‰-0.7‰. The soil squeezing effect was not obvious during the pile sinking. Field vibration test results showed that the maximum peak velocity was 0.823 mm/s in the absence of subway running, while in the presence of subway running, the peak velocity was 1.90 mm/s, which indicates that the impact on the surrounding environment is weak during pile sinking.
Key words
pile driving process /
steel pipe pile /
high frequency resonance-free hammer /
in-situ pile sinking test /
displacement
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
References
[1] 刘国彬,王卫东. 基坑工程手册[M]. 北京:中国建筑出版社, 2009.
[2] 李国维,边圣川,陆晓芩,等. 软土路堤拓宽静压PHC管桩挤土效应现场试验[J].岩土力学,2013,34(4):1089-1096.
[3] 雷华阳,李 肖,陆培毅,等.管桩挤土效应的现场试验和数值模拟[J].岩土力学,2012,33(4):1006-1012.
[4] COOKE R W, PRICE G, TARR K. Jacked Piles in London Clay: A Study of Load Transfer and Settlement under Working Conditions[J]. Géotechnique, 1979, 29(2):113-147.
[5] JONKER J. Vibratory Pile Driving Hammers for Pile Installations and Soil Improvement Projects [C]∥Proceedings of the19th Annual Offshore Technology Conference. Houston, April 27-30, 1987: 549-560.
[6] 陈岱杰,陈龙珠,郑建国. 高频振动打桩机理的试验研究[J].铁道建筑, 2006(7): 49-51.
[7] 汪金卫,陈福全,简洪钰.高频液压振动锤打桩的可打入性分析模型[J].福建工程学院学报,2009,7(1):9-15.
[8] FLOYD D, ALDINGER P B. Load Testing of Steel Sheet Piling Driven with a Vibratory Hammer[G]∥Measurement of Pavement Surface Condition 1990 : Research Papers Prepared from the 69th Annual Meeting of the Transportation Research Board, Washington, D.C.: National Research Council, 1990.
[9] BEEN K, JEFFERIES M. Soil Liquefaction[M]. London: CRC Press, 2015.
[10]施耀锋. 紧邻地铁隧道高频免共振液压锤沉桩施工技术[J].建筑科技, 2018,2(2): 30-33.
[11]徐军彪.钢管桩高频免共振沉桩在桥基施工中的应用[J].建筑施工,2017,39(7):1074-1076.
[12]陈福全, 汪金卫,李大勇,等. 高频液压振动锤打桩的应用概况与研究进展[J].岩土工程学报, 2011, 33(增刊2): 224-231.
[13]杨春柳. 钢管桩免共振施工对邻近地铁的振动影响试验研究[J].建筑施工, 2018, 40(9): 1655-1657.