Study on Dike-break Flood and Scouring: Review and Prospect

ZHANG Xin-jian,QU Geng,FAN Bei-ling,ZHU Yong-hui

Journal of Changjiang River Scientific Research Institute ›› 2019, Vol. 36 ›› Issue (4) : 9-12,38.

PDF(1277 KB)
PDF(1277 KB)
Journal of Changjiang River Scientific Research Institute ›› 2019, Vol. 36 ›› Issue (4) : 9-12,38. DOI: 10.11988/ckyyb.20171143
RIVER-LAKE SEDIMENTATION AND REGULATION

Study on Dike-break Flood and Scouring: Review and Prospect

  • ZHANG Xin-jian,QU Geng,FAN Bei-ling,ZHU Yong-hui
Author information +
History +

Abstract

Due to the serious consequences of dike break, researchers all over the world have paid great attention to dike-break flood and scouring. In this paper, we made a review on dike-break flood and scouring from aspects of theoretical research, mathematical model, and physical model test. We summarized the development, research progress, and achievements in this regard, and by depicting the advantages and shortcomings of the aforementioned three research approaches, we reckon that single approach does not meet current requirements on the study anymore. Developing a comprehensive research method integrating various approaches with wide application scope, high simulation precision could be a crucial direction for future research. Moreover, theoretical research should be strengthened, and development on monitoring instruments should be also intensified to offer technical support for flood control and disaster prevention.

Key words

dike-break flood / scouring / theoretical research / mathematical simulation / physical model test

Cite this article

Download Citations
ZHANG Xin-jian,QU Geng,FAN Bei-ling,ZHU Yong-hui. Study on Dike-break Flood and Scouring: Review and Prospect[J]. Journal of Changjiang River Scientific Research Institute. 2019, 36(4): 9-12,38 https://doi.org/10.11988/ckyyb.20171143

References

[1] SEED H B, DUNCAN J M. The Failure of Teton Dam. Engineering Geology, 1987, 24(1-4):173-205.
[2] 河南省水利厅. 河南“75?8”特大洪水灾害. 郑州:黄河水利出版社, 2005.
[3] 向立云, 姜付仁, 倪 婧. 簰洲湾98决堤情况典型调查. 灾害学, 2000, 15(2):49-52.
[4] 周雪漪.计算水力学. 北京:清华大学出版社,1995:239.
[5] RITTER A. Die Fortpflanzung Der Wasserwellen Zeitschrift Des Vereins. Deutscher Ingenieure,1892: 947-954.
[6] STOKER J J, LINDSAY R B. Water Waves. Physics Today, 1958, 11(8):28-30.
[7] SELLIN R H J. Flow in Channels.London:Macmillan Education UK, 1969:121-135.
[8] 林秉南,龚振瀛,王连祥.突泄坝址过程线简化分析.清华大学学报(自然科学版),1980,20(1):17-31.
[9] 谢任之. 溃坝坝址流量计算. 水利水运工程学报, 1982,(1):46-61.
[10] 伍 超, 吴持恭. 求解任意决口断面溃坝水力特性的形态参数分离法. 水利学报, 1988,19(9):12-20.
[11] RAUDKIVI A J. Functional Trends of Scour at Bridge Piers. Journal of Hydraulic Engineering, 1986, 112(1):1-13.
[12] MELVILLE B W, CHIEW Y M. Time Scale for Local Scour at Bridge Piers. Journal of Hydraulic Engineering, 1999, 125(10):59-65.
[13] 泰荣昱. 论河床冲刷和粗化. 武汉水利电力学院学报, 1981, (3):45-55.
[14] 秦荣昱, 胡春宏, 梁志勇. 沙质河床清水冲刷粗化的研究. 水利水电技术, 1997,28(6):8-13.
[15] 毛昶熙. 闸坝泄流局部冲刷问题(八)——局部冲刷公式综述. 人民黄河, 1989,(6):64-67.
[16] 明宗富, 刘建军, 詹义正. 高坝挑流冲刷深度计算. 长江科学院院报, 1991,8(4):51-56.
[17] 陈椿庭. 关于高坝挑流消能和局部冲刷深度的一个估算方法. 水利学报, 1963,(2):73-77.
[18] 施振兴. 用淹没度控制和计算消能戽的局部冲刷. 水利水运工程学报, 1986,(2):15-25.
[19] 李远发, 陈俊杰, 郭慧敏. 透水桩坝前冲刷坑深度影响因素探讨. 水利水电技术, 2008, 39(2):26-28.
[20] 周政杰. 溃坝水流冲刷三维数值模拟. 杭州:浙江大学, 2016.
[21] 张细兵, 范北林. 溃坝洪水演进平面二维数学模型初步研究. 长江科学院院报, 2006, 23(6):19-21.
[22] 余明辉, 张小峰. 平面二维溃堤水流泥沙数值模拟. 水科学进展, 2001, 12(3):286-290.
[23] ZHANG X F, YU M H. Numerical Simulation of Bed Deformation in Dikeburst. Journal of Hydrodynamics, 2001, 13(4):60-64.
[24] 张修忠, 王光谦. 堤防溃决的流动分析及冲刷坑计算. 泥沙研究, 2002, 27(1):18-24.
[25] LIANG L, NI J R, BORTHWICK A G L, et al. Simulation of Dike-break Processes in the Yellow River. Science in China(Series E), 2002, 45(6):606-619.
[26] ZHU Y H, VISSER P J, VRIJLING J K. A Model for Breach Erosion in Clay-Dikes∥American Society of Civil Engineers. American Society of Civil Engineers Fifth International Conference on Coastal Dynamics Barcelona, Spain, April 4-8, 2005:1-10. [27] 朱勇辉, 范北林, 卢金友,等. 唐家山堰塞湖溃坝洪水分析及泄流冲刷模拟. 人民长江, 2008, 39(22):79-82.
[28] 林明森, 陶建华. 三维溃坝问题的数值模拟研究. 水利学报, 1996, 27(7):67-74.
[29] 马福喜, 牛文臣, 孙东坡. 三维水流河床变形数学模型. 水动力学研究与进展, 1996, 11(3):241-250.
[30] 符传君, 练继建. 溃坝水流在复杂河道中传播的三维数值模拟. 水利学报, 2007, 38(10):1151-1157.
[31] SPINEWINE B, CAPART H. Intense Bed-load Due to a Sudden Dam-break. Journal of Fluid Mechanics, 2013, 731:579-614.
[32] SPINEWINE B, ZECH Y. Small-scale Laboratory Dam-break Waves on Movable Beds. Journal of Hydraulic Research, 2007, 45(Sup.1):73-86.
[33] ZECH Y, SOARES-FRAZO S, SPINEWINE B, et al. Dam-break Induced Sediment Movement: Experimental Approaches and Numerical Modelling. Journal of Hydraulic Research, 2008, 46(2):176-190.
[34] GOUTIERE L, SOARES-FRAZO S, ZECH Y. Dam-Break Flow on Mobile Bed in Abruptly Widening Channel: Experimental Data. Journal of Hydraulic Research, 2011, 49(3):367-371.
[35] 田治宗, 解吉祥. 堤防溃口口门区水力及冲淤特性模型试验研究. 人民黄河, 2003, 25(3):32-33.
[36] 陆灵威, 林斌良, 孙 健, 等. 河道溃堤水波的物理模型实验研究. 水力发电学报, 2016, 35(11):25-34.
[37] 王新强. 当卡水电站下游冲刷坑形态的试验研究. 杨凌:西北农林科技大学, 2014.
[38] 刘向宇.当卡水电站下游局部冲刷坑深度试验研究. 杨凌:西北农林科技大学, 2014.
[39] 谢任之.溃坝水力学.济南:山东科学技术出版社, 1993.
[40] 陆遐龄.三峡工程防护问题研究的回顾.中国三峡, 1995, (2):23-24.
刘心愿, 陈 栋.湖北省鄂北地区水资源配置工程夹河套段(PCCP)倒虹吸防护工程专题研究.武汉: 长江科学院, 2017:72-100.
PDF(1277 KB)

Accesses

Citation

Detail

Sections
Recommended

/