Pressurized expansive water seal is widely applied to weep holes of high head in water conservancy project. Due to many reasons, radial gate may suffer from leakage or even failure of the water seal and adapting pieces. Taking an actual project for example, most M20 stainless steel bolts on the bottom water clamping plate rotated out and were washed away in the first flood season after operation; in the second flood season, the bolts still fractured even after enlargement of the diameter of bolts (from M20 to M27) and improvement of bolts grade (from A2-70 to 10.9). In view of this, we investigated the hydraulic characteristics in the vicinity of the bottom water seal of the working radial gate via physical model test. Results unveiled that negative pressure and cavitation induced by high-velocity flow and resonance generated by flow-excited vibration are major causes of the failure of water seal system. Furthermore, through scheme optimization, we proposed an engineering countermeasure, which is to arrange baffle sill in the downstream reach near the slope of the gate slot. Test results demonstrated that flow condition in the exit segment has improved remarkably, negative pressure of water seal vanished, and flow cavitation number increased, implying evident energy dissipation and corrosion reduction effects. In addition, we recommend rigid connection instead of elastic connection between the clamping plate and the base plate in order to avoid resonance of the water seal system by keeping the natural frequency of the water seal system far from the dominant area of frequency distribution of fluctuating pressure. The research findings offer reference for the design and fault treatment of water seal system of radial gate.
Key words
radial gate /
pressurized expansive water seal /
negative pressure /
flow cavitation number /
energy dissipation and corrosion mitigation /
time-averaged pressure /
fluctuation pressure
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
References
[1] 钱军祥,魏文炜,邹柏青, 等.构皮滩水电站泄洪中孔弧形闸门充压止水设计.人民长江,2010,41(22):41-43.
[2] 赵清静,李 锋.拉西瓦水电站泄洪底孔事故闸门及门槽设计.西北水电,2010,(2):72-75.
[3] 曹 阳,徐 衡.充压式水封在二滩水电站中的应用.四川水力发电,2008,27(增3):106-108.
[4] 王 雷,莫 非.东风水电站中孔弧形闸门止水装置改造.贵州水力发电,2001,15(2):25-28.
[5] 白绍学,张绍春,李一兵,等. 高水头弧形闸门伸缩式水封止水试验研究.云南水力发电,2009,25(5):15-20.
[6] 吴杰芳,张林让,余 岭,等.闸门流激振动全水弹性模型试验的原型验证.长江科学院院报,2005,(5):62-64.
[7] 汪海潮.葛洲坝二江泄水闸弧形闸门振动研究.长江科学院院报,1993,(3):62-67.
[8] 肖兴斌,王才欢,王业红.弧形闸门突扩跌坎式通气减蚀研究进展综述.长江科学院院报,2000,17(5):1-4,8.
[9] 刘 娟. 伸缩式水封在应用中存在问题及解决方法. 甘肃水利水电技术,2012,48(6): 16-17,20.
[10] 周瑞忠,池 元. 水口电站导流底孔封堵方案中挟气对负压和气蚀的影响. 福州大学学报(自然科学版),1993,(3):73-78.
[11] 杨永森,杨永全. 掺气减蚀设施体型优化研究. 水科学进展,2000, 11(2) :144-147.
[12] 肖兴斌,王业红.弧门突扩跌坎式通气减蚀研究应用综述.中南水力发电,2001, (4):65-69.
[13] 张林让,蒋昱州,曾 平,等.向家坝导流底孔平面封堵闸门流激振动问题研究.长江科学院院报,2011,28(10):186-192.