Research and Practice of Pontoon-type Floating Row Applied in Front of Three Gorges Dam to Remove Floating Debris

CAI Ying, XIE Xue-lun, HUANG Guo-bing

Journal of Changjiang River Scientific Research Institute ›› 2016, Vol. 33 ›› Issue (10) : 63-66.

PDF(882 KB)
PDF(882 KB)
Journal of Changjiang River Scientific Research Institute ›› 2016, Vol. 33 ›› Issue (10) : 63-66. DOI: 10.11988/ckyyb.20150674
HYDRAULICS

Research and Practice of Pontoon-type Floating Row Applied in Front of Three Gorges Dam to Remove Floating Debris

  • CAI Ying1, XIE Xue-lun2, HUANG Guo-bing1
Author information +
History +

Abstract

Floating debris directly affects hydraulic project’s spillway, power generation, navigation, water quality,and landscape. Floating debris is an environmental problem in engineering, but current approaches could not meet the requirements of large-scale treatment. To improve the passive and inefficient way of treating floating debris, we present an integrated hydraulic approach of treating floating debris by blocking, guiding, and removing debris under the joint action of hydraulics of river and floating row itself. Yangtze River Scientific Research Institute carried out tests using the floating bridge-style row equipped with guiding water power in front of the Three Gorges Dam in flood season of 2014. The floating debris were blocked and guided to a certain location and were removed concentratedly. During the test the facility was proved safe and reliable after going through extreme conditions inclusive of ship collision, waves, water level fluctuation, and counter-terrorism exercises on the water, providing a protective barrier in front of the dam on water surface.

Key words

floating debris / integrated hydraulic approach / floating barrier / safety of hydropower station / in front of Three Gorges Dam

Cite this article

Download Citations
CAI Ying, XIE Xue-lun, HUANG Guo-bing. Research and Practice of Pontoon-type Floating Row Applied in Front of Three Gorges Dam to Remove Floating Debris[J]. Journal of Changjiang River Scientific Research Institute. 2016, 33(10): 63-66 https://doi.org/10.11988/ckyyb.20150674

References

[1] 袁 杰.长江漂浮物对葛洲坝电站运行的影响[J].中国三峡建设,1998,(9):34-35.
[2] 杨文俊,冯正鹏,唐祥甫,等.三峡水库漂污物治理研究与实践效果[J].水力发电学报,2009,28(6):82-87.
[3] 蔡 莹,唐祥甫,蒋文秀.河道漂浮物对工程影响及研究现状概述[J].长江科学院院报,2013, 30(8):84-88.
[4] 蔡 莹,李章浩,李 利,等.河道型水库漂浮物综合治理措施探究[J].长江科学院院报,2010, 27(12):31-35.
[5] 蔡 莹,杨 伟,唐祥甫.三峡水力一体治理电站漂浮物措施研究和实施[C]∥第四届水库大坝新技术推广研讨会论文集. 北京:中国大坝协会,2015:570-574.
[6] 田 野,春 梅.试析大坝反恐安全的关键问题[J].中国新技术新产品,2009,(3):79-80.
[7] 刘克兢.三峡工程潜在安全威胁及防护对策[J].中国人民防空,2013,274(12):34-35.
PDF(882 KB)