Blasting Test and Analysis of Stone Quarrying for Rock-fill Dam of Houziyan Hydropower Station

YANG Chen-guang ,ZHONG Quan ,LENG Zhen-dong ,YAN Peng ,LU Wen-bo

Journal of Changjiang River Scientific Research Institute ›› 2015, Vol. 32 ›› Issue (10) : 70-73.

PDF(3695 KB)
PDF(3695 KB)
Journal of Changjiang River Scientific Research Institute ›› 2015, Vol. 32 ›› Issue (10) : 70-73. DOI: 10.11988/ckyyb.20140301
ROCK-SOIL ENGINEERING

Blasting Test and Analysis of Stone Quarrying for Rock-fill Dam of Houziyan Hydropower Station

  • YANG Chen-guang1,ZHONG Quan1,LENG Zhen-dong2,YAN Peng2,LU Wen-bo2
Author information +
History +

Abstract

Good gradation is required for the filling material of concrete face rock-fill dam in order to ensure good compaction and drainage. Taking the rock-fill material quarrying at Houziyan hydropower station on Dadu river as a research background, we summarize 6 groups of field blasting test in Selonggou quarry, and analyze the main factors affecting the rock-fill material gradation based on different blasting designs and screening results. Research results show that the gradation is affected by spacing between blasting holes, length of stem blocking, and unit consumption of detonator. Before large-scale stone quarrying, blasting tests should be conducted for each impact factor in order to determine the optimal blasting parameters. Through the field blasting tests, blasting scheme and parameters that can be used to get eligible rock-fill material are obtained, and the achievements in this research can be guidance and reference for similar projects.

Key words

Houziyan hydropower station / rock-fill dam / blasting test / drilling and blasting parameters / gradation

Cite this article

Download Citations
YANG Chen-guang ,ZHONG Quan ,LENG Zhen-dong ,YAN Peng ,LU Wen-bo. Blasting Test and Analysis of Stone Quarrying for Rock-fill Dam of Houziyan Hydropower Station[J]. Journal of Changjiang River Scientific Research Institute. 2015, 32(10): 70-73 https://doi.org/10.11988/ckyyb.20140301

References

[1] 张正宇,张文煊,吴新霞,等. 现代水利水电工程爆破[M]. 北京:中国水利水电出版社,2003. (ZHANG Zheng-yu, ZHANG Wen-xuan, WU Xin-xia, et al. Modern Water Conservancy and Hydropower Engineering Blasting[M]. Beijing: China Water Power Press, 2003. (in Chinese))
[2] 于 涛,李高正. 观音岩水电站堆石坝石料开采爆破试验与分析[J]. 爆破, 2011, 28(4): 47-49. (YU Tao, LI Gao-zheng. Blasting Trial and Analysis of Stone Quarrying for Rock-fill Dam in Guanyinyan Hydropower Station[J]. Blasting, 2011, 28(4): 47-49. (in Chinese))
[3] 黄永成,刘俊杰. 巴贡水电站堆石坝填筑料生产爆破试验研究[J]. 四川水力发电,2008, 27(6):12-14. (HUANG Yong-cheng, LIU Jun-jie. Study on Blasting Test on Fill Material of Roek-fill Dam at Bakun Hydropower Station before Construction[J]. Sichuan Water Power, 2008, 27(6): 12-14.(in Chinese))
[4] 汪 辉,张延林,王小和. 微差挤压爆破在堆石坝过渡料开采中的应用[J]. 爆破,2011,28(3): 43-45. (WANG Hui, ZHANG Yan-lin, WANG Xiao-he. Application of Millisecond Compression Blasting for Transition Material Mining for Rock Fill Dam[J]. Blasting, 2011, 28(3): 43-45.(in Chinese))
[5] 姜凤海,徐文林,牛运华,等. 水布垭混凝土面板堆石坝填筑料开采爆破试验[J]. 长江科学院院报,2003,20(增刊):48-52. (JIANG Feng-hai, XU Wen-lin, NIU Yun-hua, et al. Trial Production Blasts of the Rock Filling Materials for Shuibuya Concrete Face Rockfill Dam[J]. Journal of Yangtze River Scientific Research Institute,2003,20(Sup.): 48-52.(in Chinese))
[6] 赵 伟, 王近宏. 浅谈大渡河长河坝水电站大坝堆石料爆破开采技术[J]. 四川水力发电,2012,31(4):86-89. (ZHAO Wei, WANG Jin-hong. Brief Discussion on Technologies of Blasting Mining of Rock-fill Material at Changheba Hydropower Station[J]. Sichuan Water Power, 2012, 31(4): 86-89.(in Chinese))