截流块体稳定计算是截流设计的重要基础。基于通过受力分析得出的基本表达式,结合试验和实践成果,剖析了影响截流块体稳定的主要因素,分析了截流块体稳定经典计算公式的适用条件。结果表明:在截流龙口水流垂线流速分布呈非矩形分布时,需综合考虑水深H、垂线流速系数α及相对糙度Δ/D、绕流系数ξ等影响因素;通过系列模型试验及工程实例验证,得出了考虑上述影响因素的平堵截流和立堵截流不同阶段、不同堤头形态的截流块体稳定实用计算表达式。对截流块体稳定理论及经典计算公式进行了补充和完善。
The stability calculation of river closure block is an important basis of river closure design. According to basic formulas obtained from force analysis and experimental research data, the influencing factors of block stability and the applicable conditions of classic formulas for block stability are analyzed. It is pointed out that these parameters as water depth H, vertical velocity coefficient α, relative roughness Δ/D and circumferential motion coefficient ξ should be considered when vertical velocity distribution is not rectangular in the closure gap. Through model tests and project example verification, the practical computing formulas of block stability are put forward for full-width rising and end-dump closure methods in different constructing periods and with different embankment head shapes. The research result is a supplement and improvement to the stability theory of river closure block.
[1] 伊兹巴斯C.B.河道截流水力学[M].北京:中国工业出版社,1964.(ISBASH C B. River Closure Hydraulics[M]. Beijing: China Industry Press,1964.(in Chinese))
[2] 肖焕雄.立堵截流抛石粒径计算研究[J].水电站设计,2003,(3):1-7.(XIAO Huan-xiong. Estimation Research on Riprap Grain Size for Closure by Vertical Blockade[J]. Design of Hydroelectric Power Station, 2003,(3):1-7.(in Chinese))
[3] 汪定扬.立堵截流实用水力学计算[J].水利学报,1983,(9):11-18.(WANG Ding-yang. Practical Hydraulic Calculation in End-Dump River Closure[J]. Journal of Hydraulic Engineering,1983, (9):11-18.(in Chinese))
[4] 肖焕雄.施工水力学[M].北京:水利电力出版社, 1992.(XIAO Huan-xiong. Construction Hydraulics[M]. Beijing: Water Resources and Electric Power Press, 1992. (in Chinese))
[5] 钟登华,毛寨汉.床面起伏影响下截流抛石稳定研究[J].水力发电学报,2003,(1):83-88.(ZHONG Deng-hua, MAO Zhai-han. Research on Stability of Riprap Influenced by Boundary of Riverbed During River Closure[J]. Journal of Hydroelectric Engineering, 2003,(1):83-88. (in Chinese))
[6] 郭熙灵,黄国兵,李学海.深厚覆盖层条件下施工导截流关键技术问题研究[J].长江科学院院报,2011,28(6):10-15. (GUO Xi-ling, HUANG Guo-bing, LI Xue-hai. Critical Technical Issues of Diversion and River Closure Construction Under Deep-Thickness Covering Layer Condition[J]. Journal of Yangtze River Scientific Research Institute, 2011,28(6):10-15. (in Chinese))
[7] 李学海,韩继斌,程子兵. 减轻立堵截流难度措施研究进展[J]. 长江科学院院报, 2010, 27(8):29-33. (LI Xue-hai, HAN Ji-bin, CHENG Zi-bing. Research Progress in Technology of Reducing Difficulty of Vertical Closure[J]. Journal of Yangtze River Scientific Research Institute, 2010, 27(8):29-33. (in Chinese))
[8] 左东启,顾兆勋,王文修. 水工设计手册第一卷[M].北京:水利电力出版社,1983.(ZUO Dong-qi, GU Zhao-xun, WANG Wen-xiu. Manual of Hydraulic Engineering Design(1st Volume)[M]. Beijing: Water Resources and Electric Power Press, 1983. (in Chinese))
[9] 吴望一.流体力学[M].北京:北京大学出版社,1982. (WU Wang-yi. Fluid Mechanics[M]. Beijing: Peking University Press, 1982. (in Chinese))