Flood-Releasing and Energy Dissipation of Overflow Dam atLechangxia Water Control Project

  • HUANG Zhi-min, HE Xiao-hui, ZHONG Yong-ming, CHEN Zhuo-ying, FU Bo
Author information +
文章历史 +

摘要

乐昌峡水利枢纽工程坝址处河道狭窄,溢流坝的泄洪落差和单宽流量较大,且电站尾水出水口靠近溢流坝,因此,溢流坝泄洪安全是枢纽工程的关键技术问题。通过溢流坝泄洪消能模型试验研究,对溢流坝堰面曲线、两侧收缩边墙、闸墩、挑流鼻坎等布置和体型进行了优化,改善了其运行水力特性,妥善解决了溢流坝泄洪消能防冲的问题。

Abstract

This paper studies the floodreleasing and energy dissipation of the overflow dam at Lechangxia water control project which is located in a narrow river valley. The floodreleasing safety of the overflow dam therefore is a critical technical issue as it has large water head drop and the discharge per unit width of the dam is large, and moreover, the tailrace exit of the hydropower station is in the vicinity of the dam. Based on hydraulic model tests, the hydraulic property of the overflow dam is improved and hence problems of floodreleasing and energy dissipation and scour protection are solved in this paper by optimizing the layout and configuration of overflow weir and both the contracted sidewalls as well as piers and flip buckets.

关键词

溢流坝  / 溢流堰  / 宽尾墩  / 差动式挑流鼻坎 /   / 消能  / 模型试验  / 乐昌峡水利枢纽工程

Key words

overflow dam  / overflow weir  / flaring gate piers  / differential flip bucket  / energy dissipation  / model test  / Lechangxia water control project

引用本文

导出引用
黄智敏,何小惠,钟勇明,陈卓英,付 波. 乐昌峡水利枢纽工程溢流坝泄洪消能研究[J]. 长江科学院院报. 2011, 28(5): 18-22
HUANG Zhi-min, HE Xiao-hui, ZHONG Yong-ming, CHEN Zhuo-ying, FU Bo. Flood-Releasing and Energy Dissipation of Overflow Dam atLechangxia Water Control Project[J]. Journal of Changjiang River Scientific Research Institute. 2011, 28(5): 18-22
中图分类号: TV135.2   

PDF(1612 KB)

Accesses

Citation

Detail

段落导航
相关文章

/