糯扎渡心墙堆石坝土石方调配平衡研究

陈钢, 陈朝

长江科学院院报 ›› 2009, Vol. 26 ›› Issue (6) : 60-62.

长江科学院院报 ›› 2009, Vol. 26 ›› Issue (6) : 60-62.
科技简报

糯扎渡心墙堆石坝土石方调配平衡研究

  •  陈钢, 陈朝
作者信息 +

Research on Balancing Earth-Rock Works Allocation ofNuozhadu Core Rockfill Dam

  •  CHEN  Gang, CHEN  Chao
Author information +
文章历史 +

摘要

通过分析糯扎渡心墙堆石坝土石方填筑和开挖工程之间的料源平衡和进度协调的关系,采用线性规划方法 ,结合施工中的实际因素,建立土石方调配优化数学模型。通过实际运用,达到了节约资源、节省费用、合理快速施工的目的。

Abstract

In order to balance the relation between earth-rock works excavation and earth-rock filling in the construction process of the Nuozhadu Core Rockfill Dam, an optimized mathematical model was established by adopting the linear programming method and in combination with the practical factors during construction. Through the numerical simulation of construction process, the aims of source economizing, cost saving and rationally quick construction attained.

引用本文

导出引用
陈钢, 陈朝. 糯扎渡心墙堆石坝土石方调配平衡研究[J]. 长江科学院院报. 2009, 26(6): 60-62
CHEN Gang, CHEN Chao. Research on Balancing Earth-Rock Works Allocation ofNuozhadu Core Rockfill Dam[J]. Journal of Changjiang River Scientific Research Institute. 2009, 26(6): 60-62