水布垭水利枢纽导流隧洞水力学试验研究

金宝芬, 张声鸣, 黄国兵, 廖宁

长江科学院院报 ›› 2002, Vol. 19 ›› Issue (4) : 7-10.

PDF(146 KB)
PDF(146 KB)
长江科学院院报 ›› 2002, Vol. 19 ›› Issue (4) : 7-10.
水工水力学

水布垭水利枢纽导流隧洞水力学试验研究

  •  金宝芬, 张声鸣, 黄国兵, 廖宁
作者信息 +

Hydraulic test research on construction diversion tunnels of Shuibuya Project

  •  JIN  Bao-Fen, ZHANG  Sheng-Ming, HUANG  Guo-Bing, LIAO  Ning
Author information +
文章历史 +

摘要

水布垭导流隧洞具有水头高,流量大,洞线长,地质环境差等特点,因而技术问题较多,难度较大。为此,进行了大量的试验研究。主要试验成果有:泄流能力及影响泄流能力的主要因素,压力特性及改善压力特性措施,出口消能防冲措施的比较等。这些试验成果为工程优化设计提供了科学依据。

Abstract

The diversion tunnels of the Shuibuya Project feature high head, big discharge, long tunnel line and complicated geologic conditions. For solving their hydraulic problems, a model test with a scale of 1∶80 was conducted. The paper summarizes the main results, including discharge capacity and the main factors affecting it, pressure characteristics and its improvement measures, and the comparison of energy dissipation schemes downstream the outlet. The research results offers basic data for optimal design of the diversion tunnels.

关键词

导流隧洞 / 泄流能力 / 压力特性 / 消能防冲 / 模型试验

引用本文

导出引用
金宝芬, 张声鸣, 黄国兵, 廖宁. 水布垭水利枢纽导流隧洞水力学试验研究[J]. 长江科学院院报. 2002, 19(4): 7-10
JIN Bao-Fen, ZHANG Sheng-Ming, HUANG Guo-Bing, LIAO Ning. Hydraulic test research on construction diversion tunnels of Shuibuya Project[J]. Journal of Changjiang River Scientific Research Institute. 2002, 19(4): 7-10