基于干支流双向回水顶托作用的梯级最小下泄流量保障调度研究——以酉水梯级为例

作者信息 +

Study on Guaranteed Dispatching of Minimum Discharge for Cascade Hydropower Stations Considering Bidirectional Backwater Surcharge of Mainstream and Tributary — A Case Study of the Youshui River Cascade System

Author information +
文章历史 +

摘要

针对枯水期干支流梯级最小下泄流量保障与发电调峰需求难以兼顾,且缺乏干支流双向回水顶托作用下衔接水位研究的问题,本文以酉水干流石堤水电站、支流三角滩水电站及下游石堤控制断面为研究对象,基于地形测量、水文原型观测与一维水动力学模拟,构建了干支流梯级尾水双向顶托作用下的衔接水位判别方法、梯级最小下泄流量日均或瞬时泄放条件,模拟并验证了基于干支流梯级日内交替发电的水资源调度方案。结果表明:石堤和三角滩水电站的衔接水位分别为248.0m和248.33m;当两电站分别按不低于118m3/s和39m3/s发电泄流时,即可在对方停运期间保障坝下河段不脱水及基本生境需求,并满足下游控制断面的最小下泄流量要求;与常规运行调度相比,日内交替调度使下泄流量保障率提高约30%,综合发电效益提升约9%。研究表明,基于干支流梯级双向回水顶托的日内交替发电调度在严守生态底线的同时,实现了与发电效益的协同优化,为山区干支流梯级水库生态调度提供了可行的技术路径。

Abstract

[Objectives]Current water resources management generally determines the implementation conditions for the minimum discharge of cascade hydropower stations based on the connecting water levels between upstream and downstream reaches.However, research on connecting water levels affected by backwater surcharge from the operation of cascade projects on main and tributary rivers remains insufficient. Aiming at the difficulty in simultaneously meeting the minimum discharge requirements and peak-load regulation demands for power generation of cascade reservoirs on main and tributary rivers during dry seasons, this study takes Shidi hydropower Station on the main stream of the Youshui River, Sanjiaotan hydropower Station on the Meijiang Tributary, and the controlled section at the downstream Shidi hydrological Station as the case study, and investigates the connecting water levels and the intra-day alternate water resources dispatching mechanism under the bidirectional backwater surcharge of main and tributary rivers.

[Methods]Based on topographic survey downstream of dams, prototype observations of the the water-level-discharge relationship, and one-dimensional hydrodynamic simulation, a discrimination method for connecting water levels was established to guarantee the hydraulic habitat of the main and tributary river channels as well as the minimum discharge at the controlled sections. The daily average and instantaneous discharge conditions for the minimum discharge under mutual tailwater surcharge of the two hydropower stations were analyzed. Combined with the inflow conditions and regulation capacities of the cascade projects, an intra-day alternate dispatching scheme for water resources of the mainstream-tributary cascade projects was proposed. The scheme is validated through dispatching simulation using daily inflow data from the past decade.

[Results] The results show that the connecting water levels at the tailwater sections of Shidi and Sanjiaotan hydropower Stations are 248.00m and 248.33m respectively. When the two cascade stations discharge for power generation at 118m3/s and 39 m3/s, respectively, the river reaches downstream of each dam can be prevented from drying up, with basic hydraulic habitats maintained while the counterpart station is shut down. In addition, the control index of minimum discharge at the Shidi Section can be satisfied. Simulation results indicate that, compared with the conventional operation mode, the intraday alternate dispatching increases the guarantee rate of minimum discharge for the two cascade stations and the Shidi Section by approximately 30%, and improves the comprehensive power generation benefit of cascade projects by about 9%.

[Conclusions]The intra-day alternate dispatching of water resources for cascade projects considering the bidirectional backwater surcharge of main and tributary rivers realizes the collaborative optimization of minimum discharge guarantee and power generation benefit improvement under the strict constraints of ecological red lines. This study provides a practical technical approach for ecological flow dispatching of cascade reservoir groups in mountainous mainstream-tributary river systems.

关键词

双向回水顶托 / 衔接水位 / 最小下泄流量 / 日内交替发电 / 联合调度

Key words

bidirectional backwater effect / connecting water level / minimum discharge flow / alternating generation / combined dispatching

引用本文

导出引用
孙宁宁, 陶聪, 马彪, 等. 基于干支流双向回水顶托作用的梯级最小下泄流量保障调度研究——以酉水梯级为例[J]. 长江科学院院报. 0 https://doi.org/10.11988/ckyyb.20260539
SUN Ning-ning, TAO Cong, MAO Biao, et al. Study on Guaranteed Dispatching of Minimum Discharge for Cascade Hydropower Stations Considering Bidirectional Backwater Surcharge of Mainstream and Tributary — A Case Study of the Youshui River Cascade System[J]. Journal of Changjiang River Scientific Research Institute. 0 https://doi.org/10.11988/ckyyb.20260539
中图分类号: TV213.9   

参考文献

[1]
仲志余, 邹强, 王学敏, et al. 长江上游梯级水库群多目标联合调度技术研究[J]. 人民长江, 2022, 53(2): 12-20.
(Zhong Zhi-yu, Zou Qqiang, Wang Xue-min, et al. Study on multi-objective joint operation technology of cascade reservoirs in upper reaches of Changjiang River[J]. Yangtze River, 2022, 53(2): 12-20. (in Chinese))
[2]
Yuan Long-hu, Liu Hua-xiang, Lu Yong-jun, et al. Multi-objective integrated decision method of cascade hydropower stations based on optimization algorithm and evaluation model[J]. Journal of Hydrology, 2024, 638:131533.
[3]
余启辉, 李斐. 长江流域河湖生态流量保障管理实践、成效与对策[J]. 人民长江, 2025, 56(10):105-108.
(Yu Qi-hui, Li-Fei. Management practices,effectiveness,and countermeasures for ensuring ecological flow in rivers and lakes of Changjiang River Basin[J]. Yangtze River, 2025, 56(10):105-108. (in Chinese))
[4]
赵惠萍, 汪昌树. 沅江流域水量调度方案研究[J]. 水利规划与设计, 2024(8):42-46.
(Zhao Hui-ping, Wang Chang-shu. Study on Water Quantity Dispatching Scheme in the Yuan River Basin[J]. Yangtze River, 2024, (8):42-46. (in Chinese))
[5]
Yu Chun-xue, Xu Zhi-hao, Li Yun-ying, et al. Rethinking environmental flow management strategies in reservoir operations from an integrated water quality perspective[J]. Journal of Hydrology, 2023, 626: 130196.
[6]
SL/T 820-2023, 水利水电工程生态流量计算与泄放设计规范[S]. 北京: 中国水利水电出版社, 2023.
( SL/T 820-2023,Specifications on ecological flow computation and discharge design for water and hydropower projects[S]. Beijing: China Water & Power Press, 2023. (in Chinese))
[7]
张丽亭, 逄勇, 汪静娴, et al. 基于鱼类生境所需水文-水力特征的生态流量计算方法[J]. 水利水电技术(中英文), 2025, 56(1) :100-112.
(ZHANG Liting, PANG Yong, WANG Jingxian, et a1.A method for determining the basic ecological flow of riverways through comprehensive hydrology,water conservancy,and habitat simulation analysis[J]. Water Resources and Hydropower Engineering, 2025, 56(1):100-112. (in Chinese))
[8]
国能大渡河流域水电开发有限公司.多级梯级水库水位衔接关系确定方法、装置、设备及介质[P]. 中国:CN202410894592.X,2024-10-22.
( CHN Energy Dadu River Hydropower Development Co., Ltd.Method, apparatus, device, and medium for determining water level articulation relationship of multi-stage cascade reservoirs[P]. Chinese Patent :CN202410894592.X, 2024-10-22. (in Chinese))
[9]
王建华, 王乐, 曲田, et al. 基于最小下泄流量的水位衔接模拟研究:以大渡河铜街子-沙湾电站为例[J]. 水利水电技术(中英文), 2025, 56( S1) : 547-552.
(WANG J, WANG L, QU T, et al. Simulation on connected water level under minimum discharge flow of Tongjiezi-Shawan power station in Dadu River basin[J]. Water Resources and Hydropower Engineering, 2025, 56( S1) : 547-552. (in Chinese))
[10]
王琨, 周波, 郭卫, 等. 目标生态需求下的梯级水库生态衔接水位指标构建及运用方式初探[J]. 中国农村水利水电, 2023, (6): 115-119,127.
(WANG K, ZHOU B, GUO W, et al. Preliminary research on the construction and application of ecological connected water level index of cascade reservoirs under the target ecological demand[J]. China Rural Water and Hydropower, 2023(6):115-119,127. (in Chinese))
[11]
李书飞, 阮燕云, 黄克威, et al. 基于电站调峰运行的梯级水电站衔接水位改进方法[J]. 人民长江, 2026, 55(1):248-254.
(Li Shu-fei, Ruan Yan-yun, Huang Ke-wei, et al. Research on Improved Method for Connecting Water Level of Cascade Hydropower Stations Based on Peak Regulation Operation[J]. Yangtze River, 2026, 55(1): 248-254. (in Chinese))
[12]
李一鸣, 马立亚, 孙宁宁. 沅江上游梯级水电站水位衔接关系研究[J]. 水利技术监督, 2025(10):292-295.
(Li Yi-ming, Ma Li-ya, Sun Ning-ning. Study on Water Level Connection Relationship of Cascade Hydropower Stations in the Upper Reaches of Yuanjiang River[J]. Techenical Supervision in Water Resources, 2025, (10): 292-295. (in Chinese))
[13]
段瞳, 马彪, 王天宇. 基于生态安全的雅砻江减水河段最小下泄流量保障调度研究[J]. 水利水电技术(中英文), 2025, 56(6) : 64-76.
(DUAN T, MA B, WANG T. Research on minimum discharge flow protection scheduling strategies in flow-reduced reaches of Yalong River based on ecological security[J]. Water Resources and Hydropower Engineering, 2025, 56(6) : 64-76. (in Chinese))
[14]
王琨, 马俊超. 金中梯级电站尾水水位流量关系受顶托影响研究[C]// 中国水利学会. 中国水利学会2021学术年会论文集第一分册, 2021: 104-110.
(WANG K, MA J. Study on the backwater effects on the tailwater stage-discharge relationship of the Jinzhong cascade hydropower stations[C]// Chinese Hydraulic Engineering Society:Proceedings of the 2021 Academic Annual Conference of Chinese Hydraulic Engineering Society, Volume 1, 2021: 104-110. (in Chinese))
[15]
张子平, 许江松, 黄迪. 水头衔接的梯级电站水头分配问题研究[J]. 人民长江, 2024, 55(1):242-246.
(Zhang Zi-ping, Xu Jiang-song, Huang Di. Water - head allocation in cascade hydropower stations with water - head connection[J]. Yangtze River, 2024, 55(1):242-246. (in Chinese))
[16]
谢蒙飞, 徐航, 张俊涛, 等. 支撑电网保供和消纳的梯级电站水位控制方法[J]. 人民长江, 2025, 56(3): 191-199.
(XIE M, XU H, ZHANG J, et al. Method of controlling water level in cascade hydropower stations to guarantee grid power supply and consumption[J]. Yangtze River, 2025, 56(3): 191-199. (in Chinese))

基金

国家自然科学基金重大项目课题(52394235)
长江勘测规划设计研究有限责任公司自主创新项目(CX2021Z10-2)
长江勘测规划设计研究有限责任公司自主创新项目(CX2024Z03-6)
长江勘测规划设计研究有限责任公司自主创新项目(CX2024S020)

PDF(1290 KB)

Accesses

Citation

Detail

段落导航
相关文章

/

〈 〉