PDF(1430 KB)
PDF(1430 KB)
河道采砂影响下桥墩冲刷特性试验研究
Experimental Study on Scour at Bridge Piers: Influence of River Sediment Mining
河道采砂是桥梁冲刷水毁的主要诱因之一,近年来全球河道采砂量持续增长给桥梁安全带来了严峻挑战。针对采砂河道中桥墩冲刷特性认识不清,且缺乏可靠冲刷预测方法的问题,本研究基于概化水槽试验,揭示了采砂坑位置和形态对桥墩冲刷发展过程和最大冲刷深度的定量影响。结果表明,桥墩冲刷深度主要受上游采砂坑影响;清水冲刷条件下,上游采砂坑会增大桥墩的历时冲刷深度,并延长冲刷平衡时间;浑水冲刷条件下,上游采砂坑在冲刷初期因截留来沙可使桥墩最大冲刷深度增大约120%;桥墩最大清水和浑水冲刷深度均随采砂坑长度和深度的增大而增加,随采砂坑距桥墩的距离增大而减小,当距离超过64倍桥墩直径后影响可忽略。基于理论分析与试验数据,提出了采砂河道桥墩最大清水、浑水冲刷深度预测方法,对试验样本的拟合误差分别为±5%和±15%,为采砂河段桥墩冲刷设计提供理论和方法支撑。
[Objectives] River sediment mining is one of the major causes of bridge scour-induced failures. To address the growing threat to bridge safety posed by increasing global river sediment extraction, this study aims to investigate the effects of sediment mining pits on scour at bridge piers. The goal is to quantitatively reveal the impacts of mining pit location and geometry on clear-water and live-bed scour depths, and to develop reliable predictors for the maximum scour depths at bridge piers in mining-affected reaches. [Methods] Generalized flume experiments were conducted in a water-sediment recirculating flume with a uniform sediment bed and a circular bridge pier model. Two series of tests were performed under clear-water and live-bed scour conditions. A total of 32 runs were designed by systematically varying the pit-pier spacing, pit depth, and pit length. The temporal evolution of pier scour depth was continuously measured using ultrasonic transducers installed around the pier, and the maximum scour depths were extracted from the measured time series. The responses of these scour parameters to mining pit location and geometry were quantitatively evaluated to establish empirical relationships between the pit parameters and the maximum scour depths. [Results] The experimental results show that upstream mining pits exert a greater influence on pier scour depth than downstream pits. Under clear-water scour conditions, an upstream pit increases both the temporal scour depth and the time required to reach equilibrium stage, with the influence intensifying as the pit-pier distance decreases and as the pit depth or length increases. When the upstream pit is within 8 times the pier diameter, or when its depth exceeds 4 times or its length exceeds 20 times the pier diameter, the temporal evolution of scour depth exhibits an oscillatory pattern before reaching equilibrium, indicating that the flow structure around the pier is substantially disturbed by the nearby pit. Under live-bed conditions, the scour depth exhibits a distinct initial peak due to sediment interception by the upstream pit at the early stage, which is approximately 120% larger than that without mining pit; after the pit is refilled, the scour depth decreases substantially and gradually approaches a dynamic equilibrium. The refilling process is accompanied by sediment supply from upstream, which gradually restores the sediment feed to the pier scour hole. Once the pit is completely filled, the scour depth fluctuates around a relatively stable mean value, indicating that the influence of the pit on pier scour becomes substantially weakened. The maximum clear-water and live-bed scour depths both increase with increasing pit depth and length, and decrease with increasing pit-pier distance; when the pit-pier distance exceeds approximately 64 times the pier diameter, the upstream pit effect becomes negligible. Predictors for estimating the maximum pier scour depth considering the impacts of mining pit location and geometry are proposed. The fitting errors for the present experimental data are within ±5% and ±15% for clear-water and live-bed scour conditions, respectively. In addition, two correction factors are proposed to adjust existing predictors of maximum scour depth at bridge piers under non-mining conditions for application in mining-affected reaches. [Conclusions] This study highlights that upstream mining pits are the primary concern for pier scour in mining-affected reaches. In the presence of an upstream pit, the initial peak scour under live-bed scour conditions, though transient, can be substantially larger than the long-term equilibrium scour and should be considered in bridge safety assessment during flood events. The proposed predictors and correction factors provide technical support for scour-resistant design of bridge piers in mining-affected reaches. Future work may extend the experimental conditions to non-uniform sediments, different pier shapes, and unsteady flows, and compare the proposed formulas with field observations to further validate their general applicability.
sediment mining / bridge pier / local scour / sediment transport
| [1] |
|
| [2] |
徐蔚敏. 河道采砂对涉河工程影响探讨[J]. 水利建设与管理, 2009, 29(4): 55-57.
(
|
| [3] |
王国栋, 杨文俊. 河道采砂对河道及涉水建筑物的影响研究[J]. 人民长江, 2013, 44(15): 69-72.
(
|
| [4] |
秦泗凤. 近期中国桥梁水毁事故回顾与分析[J]. 中外公路, 2022, 42(1): 133-138.
(
|
| [5] |
齐梅兰, 孟国清. 河道采沙对大桥基础安全影响研究[J]. 水动力学研究与进展(A辑), 2005, (6): 750-754.
(
|
| [6] |
吴济栋. 沙坑演变对桥下河床冲刷影响研究[D]. 北京交通大学, 2011.
(
|
| [7] |
|
| [8] |
司鹏飞, 牛小静, 余锡平. 跨/穿河建筑物上游河道采砂安全距离[J]. 南水北调与水利科技, 2017, 15(2): 143-148.
(
|
| [9] |
|
| [10] |
|
| [11] |
齐梅兰, 郐艳荣. 河床溯源冲刷影响下的桥墩冲刷[J]. 水利学报, 2017, 48(7): 791-798.
(
|
| [12] |
|
| [13] |
钟艳红, 岳红艳, 姚仕明, 等. 湘江典型河段采砂活动对河道演变影响研究[J]. 人民长江, 2021, 52(8): 10-15.
(
|
| [14] |
|
| [15] |
|
| [16] |
|
| [17] |
|
| [18] |
|
| [19] |
|
| [20] |
|
| [21] |
|
| [22] |
王路, 刘宏伟, 魏凯,
|
/
| 〈 |
|
〉 |