长江科学院院报 ›› 2018, Vol. 35 ›› Issue (4): 137-142.DOI: 10.11988/ckyyb.20161372

• 水利经济 • 上一篇    下一篇

基于改进序关系分析法的抽水蓄能电站经济效益综合评价

高瑾瑾a, 郑源b, 李涧鸣a   

  1. 河海大学 a.水利水电学院; b.能源与电气学院,南京 210000
  • 收稿日期:2016-12-30 出版日期:2018-04-01 发布日期:2018-04-16
  • 通讯作者: 郑 源(1964-),男,山东日照人,教授,博士,博士生导师,研究方向为水电站水力机械。E-mail:zhengyuan@hhu.edu.c
  • 作者简介:高瑾瑾(1993-),女,湖北宜昌人,博士研究生,研究方向为可再生能源发电。E-mail:gaojinjinhhu@outlook.com
  • 基金资助:
    国家自然科学基金项目(51579080,51339005);安徽省自然科学基金项目(1608085ME119);江苏高校优势学科建设工程资助项目(水利工程YS11001)

Comprehensive Evaluation of Economic Benefits of Pumped Storage Power Plants by Improved Order Relation Analysis Method

GAO Jin-jin1, ZHENG Yuan2, LI Jian-ming1   

  1. 1.College of Water Conservancy & Hydropower Engineering,Hohai University,Nanjing 210000, China;
    2.College of Energy & Electric Engineering, Hohai University, Nanjing 210000, China
  • Received:2016-12-30 Published:2018-04-01 Online:2018-04-16

摘要: 针对抽水蓄能电站的功能特点,提出了“辅助服务效益”的概念,建立了由财务评价、国民经济评价及辅助服务效益组成的经济效益指标体系。首先应用改进的序关系分析法确定各指标的权重值,将点赋值推广为区间赋值,从整体上提升了评价效果。然后选取非线性方法无量纲处理定量指标,三角模糊数法量化处理定性指标,最终线性加权得到各指标的综合评价值。根据某抽水蓄能电站的部分实际参数计算相关评价指标,对算法的适用性及评价的逻辑性进行了验证。研究结果可为全面评判某抽水蓄能电站的经济效益提供参考。

关键词: 抽水蓄能电站, 经济效益, 辅助服务效益, 改进的序关系分析法, 综合评价

Abstract: In view of the functional characteristic of pumped storage power plant, the concept of “auxiliary service benefit” is put forward, and the economic benefit index system of pumped storage power plants composed of financial evaluation, national economic evaluation and auxiliary service benefit is established. Firstly, the improved order relation analysis method is employed to determine the weight value of each index, and the point assignment is extended to interval assignment, hence improving the overall evaluation result. Subsequently, the quantitative indexes are processed dimensionless by non-linear method, and the qualitative indexes are quantified by the triangular fuzzy number method. Finally, the comprehensive values of the evaluation indexes are obtained via linear weighting. The applicability of the present method and the logic of the evaluation are verified through a practical case.

Key words: pumped storage power plant, economic benefit, auxiliary service benefit, improved order relation analysis method, comprehensive evaluation

中图分类号: