在回顾三峡水库长期使用问题已往研究成果和分析三峡水库初期蓄水运用以来库区泥沙淤积状况的基础上,提出了关于三峡水库排沙调度的建议。排沙调度是三峡水库运行调度的重要组成部分。排沙调度的目的是保证三峡水库大部分有效库容能长期使用;排沙调度的主要要求是在水库泥沙淤积达到初步平衡之前,仍应控制水库有效库容的年损失率小于1 000万m3/a,以及水库变动回水区上、中段无累积性泥沙淤积。汛期防洪限制水位的调整应符合上述要求。按三峡水库排沙调度方案,可以保持三峡水库大部分有效库容长期使用。
Abstract
On the basis of reviewing the previous research results for the permanent use of the Three Gorges reservoir,and analyzing the sedimentation situation since the operation of the Three Gorges reservoir,suggestions about operating mode of sediment discharging were proposed.Operating mode of sediment discharging is important for the operating mode of Three Gorges Reservoir.The purpose of operating mode of sediment discharging is to realize the permanent use of the main usable capacity of Three Gorges reservoir.Its preliminary requirements are to control the loss rate of reservoir usable storage less than 1 000×104 m3 per year before primary equilibrium of the reservoir deposition, and to resist the occurrence of the progressive deposition in the upper and middle reaches of fluctuating backwater region.The adjustment of flood control level in flood season should be in keeping with above requirements.According to the operating mode suggested,usable storage of the Three Gorges reservoir can be permanently used.
关键词
三峡水库 /
水库泥沙淤积 /
水库长期使用 /
有效库容年损失率 /
排沙调度
Key words
Three Gorges reservoir /
deposition in the reservoir /
permanent use of reservoir /
loss rate per year of reservoir usable storage /
regulation of sediment discharging
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
参考文献
[1] 林一山.毛主席重视水库寿命问题[C]∥林一山治水文选.武汉:新华出版社1992:21-24.(LIN Yi-shan.Chairman Mao Ze-dong Attaches Importance to the Problem of Reservoir Life[C]∥Selected Works of River Harness by Lin Yi-shan.Wuhan:Xinhua Press,1992:21-24.(in Chinese))
[2] 唐日长.水库淤积调查报告[J].人民长江,1964,(3):8-14.(TANG Ri-chang.Investigation Report on Sedimentation of Reservoir[J].Yangtze River,1964,(3):8-14.(in Chinese))
[3] 林一山.水库长期使用问题[J].人民长江,1978,(2):1-8.(LIN Yi-shan.Problem on the Permanent Use of Reservoir[J].Yangtze River,1978,(2):1-8.(in Chinese))
[4] 韩其为.长期使用水库的平衡形态及冲淤变形研究[J].人民长江,1978,(2):18-35.(HAN Qi-wei.Study on the Equilibrium Shape and the Change of Deposition and Scouring in the Permanent Use of Reservoir[J] Yangtze River,1978,(2):18-35.(in Chinese))
[5] 夏震寰,韩其为,焦恩泽.论长期使用库容[C]∥中国水利学会.河流泥沙国际学术讨论会论文集.北京:光华出版社,1980:753-762.(XIA Zhen-huan,HAN Qi-wei,JIAO En-ze.The Long-term Capacity of A Reservoir[C]∥Chinese Hydraulic Engineering Society.Proceedings of the International Symposium on River Sedimentation.Beijing:Guanghua Press,1980:753-762.(in Chinese))
[6] 潘庆燊.长江水利枢纽工程泥沙研究[M].北京:中国水利水电出版社,2003.(PAN Qing-shen.Study on Sedimentation Problems of the Projects in Yangtze River[M].Beijing:China Water Power Press,2003.(in Chinese))
[7] 长江水利委员会.长江三峡水利枢纽初步设计报告(枢纽工程)[R].武汉:长江水利委员会,1992.(Changjiang Water Resources Commission.Preliminary Design Report of the Three Gorges Project in Yangtze River(Project Structures)[R].Wuhan:Changjiang Water Resources Commission under the Ministry of Water Resources,1992.(in Chinese))
[8] 长江水利委员会水文局.2014年度三峡水库进出库水沙特性、水库淤积及坝下游河道冲刷分析[R].武汉:长江水利委员会水文局,2015.(Bureau of Hydrology of Changjiang Water Resources Commission.Analysis on Features of Incoming and Outflowing Water and Sediment Discharges,Reservoir Sedimentation and Downstream Scouring of TGP in 2014[R].Wuhan:Bureau of Hydrology of Changjiang Water Resources Commission,2015.(in Chinese))
[9] 潘庆燊,陈济生,黄 悦,等.三峡工程泥沙问题研究进展[M].北京:中国水利水电出版社,2014.(PAN Qing-shen,CHEN Ji-sheng,HUANG Yue,et al.Research Advances in Sedimentation Problems of the Three Gorges
Project[M].Beijing:China Water Power Press,2014.(in Chinese))